An unpaid construction invoice can put wages, suppliers and the next stage of a project under pressure. The Building and Construction Industry Security of Payment Act 1999 (NSW), commonly called SOPA or the Security of Payment Act, provides a statutory process for claiming progress payments and resolving payment disputes quickly.

For a subcontractor not paid in NSW, that process may lead to an adjudication determination and an enforceable judgment without first conducting a full construction contract trial. For principals, head contractors and homeowners receiving a payment claim, the immediate task is different: recognise the claim, calculate the response deadline and serve a proper payment schedule.

The Act works through strict procedural steps. A strong claim can fail because it was served too early or an adjudication application was late. A respondent with genuine complaints about defects can lose the opportunity to rely on those complaints in the statutory recovery process by missing the payment schedule deadline.

Lachlan Ly, Associate at GopherWood Lawyers, explains the NSW Security of Payment Act, the deadlines that commonly catch parties out and the records worth assembling before a dispute escalates.

01 Who can claim under the Security of Payment Act in NSW?

Section 8 gives a person who has undertaken to carry out construction work, or supply related goods and services, under a construction contract an entitlement to a progress payment. That statutory entitlement does not depend on the contract providing a monthly progress payment mechanism.

Depending on the work and contractual relationship, claimants can include builders, subcontractors, suppliers, plant hirers and construction consultants. A construction contract can be written, oral or partly both. An unsigned subcontract is therefore not necessarily the end of the inquiry, although proving its terms may be harder.

The definitions of construction work and related goods and services in sections 5 and 6 matter. Not every debt associated with a building business qualifies. The work, its location, the relevant contract and the identity of the party liable to pay must all be checked.

Section 8(2) also restricts entitlement where the construction contract does not comply with section 4 of the Home Building Act 1989 (NSW), or involves residential building work done in contravention of section 92 of that Act. Licensing and home building compensation requirements are not merely administrative issues to consider after preparing the claim.

Can builders claim against owner-occupiers?

Yes, for owner-occupier construction contracts entered into on or after 1 March 2021, subject to the Act's requirements. Building Commission NSW confirms that the previous laws continue to apply to contracts entered into before that date.

It is therefore incorrect to say that all owner-occupier contracts remain excluded by section 7(2)(b). The definition of an exempt residential construction contract in section 4 must be read with the applicable Regulation and transitional position. The terminology also matters when calculating payment due dates.

For example, a homeowner receiving a builder's statutory claim under a recent renovation contract should not ignore it because the project is their family home. Defects and incomplete work should be addressed promptly in a payment schedule.

02 What has changed under NSW SOPA, and do the 2026 reforms apply?

The Building and Construction Industry Security of Payment Amendment Act 2018 (NSW) introduced important changes commencing on 21 October 2019. For contracts within the amended regime, reference dates were removed as the organising mechanism for progress payment claims. Section 13 instead provides monthly statutory claim opportunities and expressly permits a claim on and from termination.

The contract's formation date remains important. Older contracts can attract earlier rules, so a current invoice should not automatically be assessed under the latest provisions merely because it was issued in 2026.

Later developments include the owner-occupier changes commencing on 1 March 2021 and the section 8 licensing and insurance restriction appearing in the current consolidation from 20 August 2024.

The most recent amending legislation is the Fair Trading and Building Legislation Amendment Act 2026 (NSW), which received assent on 14 August 2026. For security of payment purposes its change is a narrow one: it replaces the Act's references to a “business day” with “working day”, to align the Act with the Interpretation Act 1987 (NSW). That amendment commences on a date to be proclaimed, and the official consolidation still shows it as not commenced. Until it does, deadlines continue to be counted in business days as defined in section 4 of the Act, which excludes weekends, public holidays and 27 to 31 December.

The 2026 Act does not change the owner-occupier position, create a separate regime for excluded amounts or alter the number of days allowed for any step described below. Because the counting rule will change when the amendment commences, check the current version of the Act whenever a deadline falls near the end of December or early January.

Building Commission NSW publishes scheme guidance and information about compliance and authorised nominating authorities. An adjudication application nevertheless follows the statutory nomination process; a complaint to the regulator does not replace it or stop its clock.

03 How do I make a valid payment claim in NSW?

Section 13 permits a claimant to serve a payment claim on the person who is or may be liable under the construction contract. Under section 13(2), the claim must identify the construction work or related goods and services, indicate the claimed amount and state that it is made under the Act.

Use clear wording: “This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW).” The Act requires that statement, so do not rely on older material describing the period when it was not generally required.

Identify the project, contract, claim period and valuation. Separate original scope, variations, previous payments, retention and the balance sought. A claim saying only “building works, balance outstanding” invites an avoidable dispute about what the respondent was being asked to assess.

When can the claim be served?

Under section 13(1A), a claim may be served on and from the last day of the month in which work was first carried out or related goods and services first supplied, and on and from the last day of each subsequent month. Section 13(1B) allows an earlier contractual claim date in a particular month.

Section 13(1C) permits a payment claim on and from the termination date. Termination does not itself extinguish access to the statutory process, although entitlement and valuation still require careful analysis.

The general restriction is one payment claim in a particular named month under each construction contract. The Act accommodates contractual additional claims and the termination entitlement. Previously claimed but unpaid amounts can be included in a later claim, but amounts already paid must be credited.

What does the 12-month limit mean?

Section 13(4) permits service within the period determined under the contract or within 12 months after the work to which the claim relates was last carried out, or the related goods and services last supplied, whichever is later. This is not simply a rule that every invoice expires on its first anniversary.

Check the last relevant work, the contract's claim period and the character of the amount sought. Retention release and final claims need particular attention. Do not assume a small return visit restarts every statutory entitlement.

Finally, prove service. Keep the complete claim, attachments, recipient details and delivery evidence. Check statutory service requirements and contractual methods before choosing email, a portal, post or personal delivery.

04 Does a head contractor need a supporting statement?

Section 13(7) prohibits a head contractor from serving a payment claim on the principal unless it is accompanied by the required supporting statement. The statement concerns payment of subcontractors and must comply with the prescribed requirements.

This obligation is distinct from proving the value of the head contractor's work. A valuation spreadsheet or subcontractor payment report is not automatically a substitute for the required statement.

Before signing, reconcile subcontractor claims, payments and disputed amounts. Record any qualifications using the proper form and obtain reliable information from accounts and project staff. Knowingly providing a false or misleading supporting statement can have consequences beyond the underlying payment dispute.

Respondents should obtain advice about an absent or defective statement rather than assume that it allows them to ignore the payment claim. Compliance obligations and the legal consequences for a claim are separate questions.

05 What is a payment schedule, and what happens if I miss it?

A payment schedule is the respondent's formal answer to a payment claim. Under section 14, it must identify the claim and indicate the amount the respondent proposes to pay, called the scheduled amount.

If that amount is less than claimed, the schedule must explain why. If payment is being withheld, it must give the reasons for withholding it. A zero-dollar schedule is possible, but the reasons still need to be expressed.

The deadline is the earlier of the contractual response period and 10 business days after service of the payment claim. A contract requiring a response sooner than 10 business days must not be overlooked.

Address the actual dispute: incomplete quantities, defective work, disputed variation instructions, previous payments, retention, contractual deductions or delay-related claims. Explain the relevant contractual basis and calculation. “Not approved” rarely tells the claimant enough about the real objection.

No schedule and no payment

Section 14(4) makes a respondent that fails to provide a schedule within time liable for the claimed amount on the payment due date. If it remains unpaid, section 15 provides debt recovery and adjudication options, subject to their requirements.

In section 15 debt proceedings, the respondent cannot bring a cross-claim against the claimant or raise a defence concerning matters arising under the construction contract. Genuine defects allegations do not automatically answer the statutory debt.

That does not eliminate every possible issue. Whether there was a qualifying contract, a valid payment claim and effective service can remain important. The distinction is between challenging statutory preconditions and attempting to reopen the contractual merits.

A schedule was served, but its amount was not paid

Section 16 addresses non-payment of the scheduled amount. The claimant may pursue the unpaid scheduled amount as a debt or use adjudication, subject to the Act. The debt recovery route also restricts contractual defences and cross-claims.

Do not confuse acknowledging an amount with paying it. A payment schedule proposing payment later does not necessarily alter the statutory due date.

06 What are the NSW Security of Payment Act deadlines?

Section 11 generally requires payment by a principal to a head contractor within 15 business days after a claim is made, or an earlier contractual date. Payment to a subcontractor is generally due within 20 business days, or an earlier contractual date. These rules exclude exempt residential construction contracts.

For an exempt residential construction contract, section 11(1C) uses the express contractual due date. If there is no express provision, payment is due 10 business days after the payment claim is made. The homeowner's payment schedule deadline is a separate obligation.

The following table summarises the key steps under sections 14, 17, 20, 21 and 27. It is a planning aid, not a substitute for calculating deadlines from the actual service events.

Key NSW SOPA steps and business-day deadlines
StepTimeframePractical point
Payment scheduleEarlier of the contractual period and 10 business days after serviceRecord service immediately and include withholding reasons.
Principal pays head contractor15 business days after the claim, or earlier contractual dateDifferent rules apply to exempt residential contracts.
Subcontractor payment20 business days after the claim, or earlier contractual dateCheck the applicable contract category.
Adjudication of reduced schedule10 business days after receiving the scheduleDo not wait for the payment due date.
Adjudication of unpaid scheduled amount20 business days after the payment due dateIdentify the unpaid balance accurately.
No-schedule adjudication noticeWithin 20 business days immediately following the payment due dateGive the respondent five business days to provide a schedule.
No-schedule adjudication applicationWithin 10 business days after that five-business-day period endsKeep proof of the notice's receipt.
Adjudication responseLater of five business days after receiving the application and two business days after receiving acceptance noticeA qualifying payment schedule is required.
DeterminationGenerally 10 business days from the applicable section 21 triggerThe trigger depends on response entitlement and lodgment.
SuspensionAt least two business days after the required noticeConfirm a statutory suspension entitlement first.

Business days are not simply ordinary trading days. Check the statutory definition, NSW public holidays and the year-end exclusion before calculating a deadline.

Maintain separate entries for the claim service date, schedule deadline, payment due date and adjudication deadline. A negotiation, promised payment or regulator complaint should never be treated as stopping a statutory period without a proper legal basis.

07 How do I make an adjudication application under SOPA?

Section 17 provides different pathways depending on whether the respondent scheduled less than claimed, failed to pay the scheduled amount, or provided no schedule and failed to pay. Choosing the correct pathway determines the application deadline and whether an additional notice is necessary.

If there is no schedule and no payment, the claimant must first give the prescribed notice of intention within the statutory period and allow five business days for a schedule. The application follows within the further 10-business-day window. This second opportunity is not a reason for respondents to disregard the original deadline.

An adjudication application is made in writing to an authorised nominating authority, with the required material and fee, and a copy must be served on the respondent. Prepare the application before the last afternoon.

Build an application the adjudicator can assess

Explain the contract, work, valuation and disputed issues in a coherent sequence. Include the payment claim, service evidence, payment schedule if any, relevant contract terms, variation instructions, photographs, delivery records and payment reconciliation.

For each disputed variation, show who instructed it, what changed, when the work occurred and how the price was calculated. For measured work, link quantities to drawings or records. A large document bundle without an explanation is not persuasive merely because it is large.

Assess proportionality. Adjudication involves nomination and adjudicator fees, preparation costs and the commercial risk of recovering from the respondent. A favourable determination does not guarantee that an insolvent company can pay.

What can the respondent put in an adjudication response?

Section 20 permits a response only where the respondent provided a payment schedule within the original statutory period or the section 17 second-chance period. The response deadline is the later of the two periods identified in the table.

The respondent cannot introduce reasons for withholding payment that were not included in its payment schedule. The schedule therefore sets important boundaries for the later response. Develop the evidence supporting the reasons already given; do not assume entirely new deductions can be added.

08 What happens after an adjudication determination?

The adjudicator determines the amount payable, the due date and applicable interest under section 22. The process is designed to produce an interim payment decision, not a final trial of every claim arising from the project.

Section 21's timing rule needs care. Where the respondent is entitled to respond, the usual 10-business-day determination period runs from lodgment of the response or, if none is lodged, expiry of the response period. Otherwise, it runs from service of the adjudicator's acceptance notice on both parties. The parties may agree to further time.

If the adjudicated amount is not paid as required, the claimant can obtain an adjudication certificate through the authorised nominating authority. Section 25 allows that certificate to be filed as a judgment for a debt in a court of competent jurisdiction, accompanied by the required affidavit concerning unpaid amounts.

Filing the certificate is not a new hearing of the building account. Section 25 restricts cross-claims, contractual defences and challenges to the determination in proceedings to set aside the judgment. It also imposes a payment-into-court requirement in connection with such proceedings.

Enforcement still requires commercial judgment. Check the debtor's correct legal identity, payments received and financial position before selecting enforcement measures. Keep an updated reconciliation so that the judgment and enforcement steps do not overstate the balance.

09 Can I suspend construction work if I have not been paid?

Section 27 permits suspension where the statutory requirements are satisfied and at least two business days have passed since the relevant notice of intention under section 15, 16 or 24 was given. An overdue ordinary invoice does not, by itself, establish every requirement.

A compliant statutory suspension carries protections against liability for losses caused by the suspension. Section 27 also addresses losses or expenses where the respondent removes work from the contract because the claimant exercised the suspension right.

The statutory right continues until the end of three business days immediately following receipt of the relevant payment. Confirm the resumption position promptly after funds arrive.

Before stopping, check the claim, service, payment due date, notice and site arrangements. An invalid suspension can expose the contractor to allegations of breach. Preserve safety, security and work records even where the payment dispute has become heated.

10 Can an adjudication determination be challenged in court?

Judicial review is available for jurisdictional error, but it is not a general appeal on valuation or contractual merits. Losing a disputed variation does not itself show that the adjudicator acted outside jurisdiction.

In Chase Oyster Bar v Hamo Industries [2010] NSWCA 190, the Court of Appeal confirmed the Supreme Court's supervisory power where the section 17(2)(a) notice requirement had not been met. The decision illustrates why statutory application conditions matter.

In Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4, the High Court held that the NSW scheme excludes judicial review for non-jurisdictional error of law on the face of the record. Identifying a legal error is therefore not enough.

Section 32 preserves final rights under the construction contract. Parties can pursue final resolution in the appropriate forum, with adjustments for payments made through the statutory process. Judicial review and final contractual proceedings serve different purposes.

Obtain advice immediately if a determination appears jurisdictionally defective. Do not assume that starting a challenge automatically stays payment or enforcement.

11 What retention money and record-keeping obligations should contractors check?

Part 2 of the Building and Construction Industry Security of Payment Regulation 2020 (NSW) regulates retention money held by head contractors for projects with a value of at least $20 million. The threshold concerns project value, not the size of an individual subcontract.

The requirements include holding relevant retention money in a trust account with an authorised deposit-taking institution, separating it from operating funds, complying with withdrawal restrictions and maintaining trust records.

Building Commission NSW also explains notification requirements when accounts are established. If a project reaches the threshold after the head contract begins, the timing rules affect which later subcontracts are captured.

Subcontractors should reconcile retention deductions against contract terms and release milestones. Head contractors should not assume that money appearing in a bank balance is available to meet general business debts.

Practical habits that prevent avoidable disputes

  • Record the correct contracting entities and ABNs before work starts.
  • Keep variation instructions, site diaries and delivery evidence together.
  • Review statutory deadlines when claims arrive, not at the next accounts meeting.
  • Separate disputed amounts from amounts accepted as payable.
  • Do not assume upstream non-payment excuses downstream non-payment.
  • Keep settlement discussions separate from compliance with running deadlines.

12 FAQs about the Security of Payment Act NSW

Is the security of payments act the same as SOPA?

Yes.

People often search for “security of payments act”. In NSW, the relevantldquo;Security of payments act

People often search for “security of payments act”. In NSW, the relevantrdquo;,

People often search for “security of payments act”. In NSW, the relevantldquo;SOPA

People often search for “security of payments act”. In NSW, the relevantrdquo; and

People often search for “security of payments act”. In NSW, the relevantldquo;the Security of Payment Act

People often search for “security of payments act”. In NSW, the relevantrdquo; all refer to the same law. In NSW, the relevant legislation is the Building and Construction Industry Security of Payment Act 1999, commonly called SOPA or the Security of Payment Act.

What should a subcontractor not paid in NSW do first?

Check the contract, last work date, claim opportunity and payment records. Prepare a compliant payment claim and retain proof of service. If a schedule has already arrived, calculate the adjudication deadline immediately.

Does a payment claim NSW need to mention the Act?

Yes. Section 13(2)(c) requires the claim to state that it is made under the Act. Include an express statement that it is made under the Act. Older contracts require a separate transitional analysis.

Can I send a payment schedule saying nothing is payable?

Yes. Identify the payment claim, state the scheduled amount as zero and explain the reasons. Serve it within the applicable deadline and preserve supporting evidence.

Should I wait until payment is overdue before making an adjudication application?

Not where the application challenges a schedule proposing less than claimed. That pathway generally has a deadline of 10 business days after receiving the schedule, which may expire before payment falls due.

Is an adjudication determination the final result?

It establishes an enforceable interim payment obligation, subject to the Act. Section 32 preserves final contractual rights, but pursuing those rights does not automatically excuse compliance with the determination.

13 How GopherWood Lawyers can assist

GopherWood Lawyers acts in building and construction disputes, including security of payment and adjudication disputes. We can assess claims, schedules, service evidence and adjudication options.

Where the dispute extends beyond an interim payment, we can advise on construction contract and commercial disputes and construction delays and project disputes.

Call 02 9160 2157 or contact GopherWood Lawyers to discuss your legal options.

This article provides general information about Australian law as at 20 November 2026. It is not legal advice. Your contract date, work, service evidence and payment history can change the outcome.

14 Sources and further reading

  1. NSW Legislation: Building and Construction Industry Security of Payment Act 1999, current version and amendment status
  2. NSW Parliament: Fair Trading and Building Legislation Amendment Bill 2026
  3. Building Commission NSW: Changes to Security of Payment laws
  4. AustLII: Section 13, payment claims
  5. AustLII: Section 8, right to progress payments
  6. AustLII: Section 11, payment due dates
  7. Building Commission NSW: Applying for adjudication
  8. AustLII: Section 20, adjudication responses
  9. AustLII: Section 21, adjudication procedures
  10. AustLII: Section 27, suspension of work
  11. Building Commission NSW: Retention money
  12. AustLII: Building and Construction Industry Security of Payment Regulation 2020
  13. NSW Caselaw: Chase Oyster Bar v Hamo Industries [2010] NSWCA 190
  14. AustLII: Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4